The Deethanizer equipment was part of a Refinery Revamp.
Special steel material meeting HIC resistant properties
was used for the fabrication of the equipment including
Deethanizer Column. Petrosin's scope of work included
Engineering, procurement, fabrication and shipment to
Benghazi.
Project Highlights
Year
Completed :
1991
Location
:
Benghazi, LIBYA
Client
:
Zuetina Oil Company,
LIBYA
Capacity
:
410 PSIG
Major
Equipment :
Deethazer Tower
Type
of Contract :
Engineering, procurement,
fabrication & shipment to Benghazi
Scope
of work :
Fabrication of 1.625"
thick and size ID 8' -8" x 92' - 9" S/S X 110' overall
lengh X 120m.Ton deethanizer tower meeting stringent
requirements of chemical compositions namely manganese,
phosporus, sulphur, carbon and carbon equivalent.